ROShell FZC and JWT Solutions FZE Complete FAT and Prepare First Shipment for Almaty CHP-3 Water Treatment Project

ROShell FZC and JWT Solutions FZE Complete FAT and Prepare First Shipment for Almaty CHP-3 Water Treatment Project

Fujairah, United Arab Emirates | September 2026

Major Project Delivery Milestone

ROShell FZC and JWT Solutions FZE have achieved a significant delivery milestone for the Almaty CHP-3 Water Treatment Project in Kazakhstan following the successful completion of Factory Acceptance Testing and the preparation of the first 11 Reverse Osmosis units for shipment from the United Arab Emirates.

The project comprises an integrated industrial water treatment solution incorporating Ultrafiltration, Reverse Osmosis and Electrodeionization technologies, together with the associated process and auxiliary systems.

Successful FAT Completed in the UAE

Factory Acceptance Testing was successfully completed in mid-August 2026 at ROShell FZC’s manufacturing facility in the UAE, in the presence of the customer’s representative.

The FAT confirmed that the manufactured equipment complies with the approved project requirements and is ready to proceed to the delivery stage.

First Shipment of 11 RO Units

The first shipment comprises 11 RO units manufactured and integrated for the Almaty CHP-3 project.

The units are undergoing final dispatch preparations before shipment from the UAE to Kazakhstan. Additional equipment packages will follow in accordance with the overall project implementation schedule.

Integrated Engineering and UAE-Based OEM Manufacturing

The Almaty CHP-3 project demonstrates the combined capabilities of JWT Solutions FZE and ROShell FZC, bringing process engineering, project execution, system integration and UAE-based OEM manufacturing together within one coordinated delivery structure.

JWT Solutions FZE is responsible for process engineering, system design and integration, project management and overall project execution.

ROShell FZC provides UAE-based OEM manufacturing, assembly, equipment integration, quality control and Factory Acceptance Testing.

One Coordinated Delivery Model

Process Engineering → System Design → OEM Manufacturing → System Integration → FAT and Quality Assurance → Delivery → Commissioning

This integrated approach provides customers with closer control over engineering interfaces, manufacturing quality, project schedules and final system performance.

Comment from ROShell

“The successful completion of FAT and the preparation of the first 11 RO units for shipment represent an important milestone for the Almaty CHP-3 project.

Combining JWT Solutions FZE’s engineering and system integration expertise with ROShell FZC’s UAE-based OEM manufacturing capabilities gives us closer control over quality, schedules and execution, while providing customers with one coordinated delivery approach from design through commissioning.”

Thomas Redko
Managing Director, ROShell FZC

International Project Capability

This milestone reinforces the United Arab Emirates as a base for engineering, OEM manufacturing and international delivery of advanced water treatment systems for power, industrial and infrastructure projects.

Project at a Glance

Project: Almaty CHP-3 Water Treatment Project
Country: Kazakhstan
Sector: Power Generation
Technologies: Ultrafiltration, Reverse Osmosis and Electrodeionization
Milestone: FAT completed and first shipment in preparation
First shipment: 11 RO units
Engineering and system integration: JWT Solutions FZE
OEM manufacturing: ROShell FZC, UAE

Contact ROShell

Email: sales@roshell.net
Telephone: +971 9 277 8135
Mobile / WhatsApp: +971 54 731 2194
Location: Fujairah Free Zone 2, United Arab Emirates

‍

‍

Engineering Articles

For technical insights, design explanations, and industry commentary
Need a custom solution?
Request a quote or speak with our engineering team to discuss your water treatment project, OEM fabrication requirements, or complete system solution.